Menu Side

Road Border Crossing in Krościenko

Project: Road Border Crossing in Krościenko
Investor/General Contractor: Krośnieńskie Przedsiębiorstwo Budowlane w Krośnie SA
Time of construction: 2002-2003
Cost of works: 4 221 000 PLN


Scope of works executed by Elektromontaż Rzeszów:

  • power supply and lighting installations
  • lightning installation
  • gutter heating installation
  • assembling of generator with automatic start
  • computer structural network
  • fire detection and alarm systems
  • teletechnical network
  • telephone installation
  • intrusion alarm system
  • access control systems
  • installation of radioactive materials detection
  • electrical tests and start-up