Metropolitan Warszawa

Project: Metropolitan Warszawa
Investor: Hines Polska Sp. z o.o.
General Contractor:  
Hochtief Polska 
Time of construction: 2001-2003
Cost of works: 12 000 000 PLN


Metropolitan is the most exclusive Polish office building with the highest standard, triple A (AAA). The design of building was made by world famous architect Sir Norman Foster. The project consists of three independent 7-floors building placed on pentagon plan.  

Scope of works executed by Elektromontaż Rzeszów: 

  • preparation of workshop and as-built documentation, 
  • MV switchgears, cable lines, transformer station
  • generator
  • busbars, LV main switchgear with backup system
  • floors distribution boards
  • power supply for motors control 
  • electrical cabling 
  • electrical installation for ventilation, air-conditoning, pipes hesting
  • internal and external lighting
  • lighting control
  • tests and start-up of installation


Metropolitan Awards:

  • Worldwide Award 2004 - from RIBA with asssociation with The Architectural Review
  • „Best Overall Project 2003" award from the Construction Journal
  • MIPIM Award in the Bussines Category at the international real estate trade tairs in Cannes.
  • The Platinum Drill - the 1st prize in Bosch competition for Polish companies