Menu Side
Road Border Crossing in Medyka
Project: Road Border Crossing in Medyka
Investor/General Contractor: Biuro Obsługi Inwestycyjnej w Przemyślu
Sp. z o.o.
Time of construction: 1998-2002
Cost of works: 2 500 000 PLN
Elektromontaz Rzeszów executed structural cabling for following facilities:
- main building of The Border Guard and The Customs
- building of people crossing
- building of bus crossing
Scope of works executed by Elektromontaż Rzeszów:
- teletechnical network
- fiberoptic cables
- construction of main distribution points
- construction of indirect distribution points
- execution of electrical points
- installation of UPS units
- installation of generator with automation with power 250 kVa
- outdoor lighting
- modernization of transformer station
- control and signalling installations
- tests of installations and fibreoptics cables